Taiwan’s Formosa 4 offshore wind project has passed a key pre-construction milestone after classification society DNV certified the turbine support structure design, Inspenet reports. The 495 MW development, sited off Miaoli County in the Taiwan Strait, is being developed by Synera Renewable Energy and is designed to generate sufficient electricity for around 500,000 homes.
The project site covers approximately 58 square kilometres at a distance of around 20 kilometres from the coast of Tongxiao, in water depths of between 57 and 64 metres. The array will comprise up to 35 turbines rated at 14 to 15 MW each, to be installed on jacket foundations — steel lattice structures suited to the site’s depth range.
DNV independently evaluated the structural design against applicable international standards and the project’s specific engineering requirements, with the assessment aimed at identifying and reducing technical risks before manufacturing begins. Robert Anderson, Synera’s project director for Formosa 4, stated that the independent review gives the team greater confidence as it prepares for subsequent development phases.
Synera secured its 495 MW capacity allocation in late 2022 during the first round of Taiwan’s third-phase zonal development programme. The developer’s portfolio in the country includes Formosa 1, Taiwan’s first offshore wind farm, which came online in 2017, and the 376 MW, 47-turbine Formosa 2, also off the Miaoli coast. Formosa 4 is the third project in that series.
Taiwanese manufacturer Century Wind Power holds the contract to fabricate all 35 jacket foundations and coordinate the broader supply package — an arrangement Synera has described as reflecting its commitment to Taiwan’s local content policy. CDWE, DEME’s Taiwanese joint venture, will handle transport and installation of the foundations and the offshore substation as well as scour protection works, deploying the Green Jade — identified as the first floating installation vessel of its kind to be designed and built in Taiwan.
Why it matters
DNV’s Vice President of Renewable Energy Certification Mette Redanz argued the declaration goes beyond demonstrating compliance — it “proves that the critical infrastructure meets the project requirements and site conditions,” giving developers and investors a basis for informed risk management. Anderson separately noted the assessment provides the team with greater confidence going into the next development phases. Identifying structural problems before manufacturing rather than during construction also avoids the more expensive remediation that follows once fabrication is under way.
What to watch next
With the design certification secured, Synera can advance to foundation fabrication and offshore installation. The timeline of that work will determine when Formosa 4 connects to the grid.