A data centre in Falun, Sweden, draws all of its electricity from hydropower and wind and channels waste heat from its servers into the city’s district heating network, The Cooldown reports. The facility, operated by EcoDataCenter, is framed in prefabricated cross-laminated timber panels rather than the steel and concrete typical of conventional builds.
The Falun installation carries an 80 MW capacity, equivalent to the electricity demand of roughly 60,000 homes, with 75% of supply sourced from hydropower and the remaining 25% from wind. Around 70% of its compute is allocated to artificial intelligence workloads; disclosed tenants include DeepL, the Germany-based AI translation platform, CoreWeave, and Mistral, with Nvidia Blackwell chips deployed in the racks.
EcoDataCenter’s sustainability report places the facility’s power usage effectiveness at 1.15, against an EU sector average of 1.36 — a score of 1.0 representing perfect efficiency. For supply continuity, backup generators run on hydrotreated vegetable oil, a fuel derived from waste vegetable oils and animal fats.
Sweden’s climate substantially reduces the cooling load. Outside air below 20°C serves as the primary cooling medium without drawing on water supplies; above that threshold, rooftop equipment cools incoming air via water mist fed from a nearby lake that previously supplied the city’s drinking water. Liquid-cooled racks, handling newer chip generations that transfer heat directly into fluid, operate through a closed-loop arrangement that John Wernvik, who leads the company’s external relations and sustainability work, told the outlet requires no external water input.
Rather than venting waste heat, the facility uses it to dry wood pellets that supply Falun’s district heating network — underground pipes distributing heated water to homes and businesses across the city. Falun’s local government initiated the project in 2010; the first phase opened in 2019. EcoDataCenter reports that 90% of its suppliers are drawn from the local area and that 60% of capital expenditure remains within the region. “I’m biased, but we believe that we build data centers in a somewhat different way,” Wernvik told the outlet.
Why it matters
The company’s sustainability report records a facility PUE of 1.15 against the EU sector average of 1.36. Wernvik told the outlet that the cross-laminated timber structure substantially cuts the pollution associated with conventional construction materials.
What to watch next
A second EcoDataCenter site in Borlänge is planned to reuse the infrastructure of a former paper mill — including its power connections, water supply, and district heating integration — with the first phase scheduled to open in 2027. EcoDataCenter expects the project to create 200 to 300 jobs, broadly matching the workforce the mill employed before it closed in 2021.